Dashuikeng 110kV Booster Station Completes Its Primary & Secondary Electrical Equipment Installation

October 25, 2017 marked the completion of primary and secondary electrical equipment installation as well as the cable laying and wiring for Dashuikeng wind power project’s 110kV booster station.

Posted on 2017-10-25 03:42

Dashuikeng Wind Turbine Project Marks Its First Hoisting

After careful preparation and deployment in the previous period, on August 12, 2017, the first fan of the Dashuikeng wind power project started to be hoisted.

Posted on 2017-08-12 03:31

The First Five Sets of Wind Turbine Equipment of Dashuikeng Wind Power Project Arrive at the Site as Planned

On June 30, 2017, the first five sets of V110-2MW wind turbine equipment (engine room, hub, blades, etc.) were delivered to the construction site of Dashuikeng wind power project on time.

Posted on 2017-06-30 03:18

Safety is Our First Priority at All Times ——Construction Project Department Holds Fire Emergency Drills

As the Chinese saying goes that “Hidden danger is more perilous than the open flame, prevention is better than disaster relief, the responsibility is as extremely heavy as Mount Tai,”

Posted on 2017-06-15 01:41

Closed-Loop Management Enhances Execution Efficiency

Since the start of the construction of Dashuikeng wind power project, Hanas constructors were confronted with complicated external construction environment and urgent task objectives.

Posted on 2017-06-05 01:30

Turbine Model for Dashuikeng and Shijiawan Wind Farms Chosen

From October 2016 to January 2017, the management of Ningxia Hanas New Energy Group and technical staff of Hanas Engineering Construction and Management Company jointly conducted field research and visited domestic turbine manufacturers

Posted on 2017-01-23 09:26

As the last hammer fell, 16 by-selection fan position marked pile all finally hit the ground, the last...