Dashuikeng 110kV Booster Station Completes Its Primary & Secondary Electrical Equipment Installation

October 25, 2017 marked the completion of primary and secondary electrical equipment installation as well as the cable laying and wiring for Dashuikeng wind power project’s 110kV booster station.

Posted on 2017-10-25 03:42

Dashuikeng Wind Turbine Project Marks Its First Hoisting

After careful preparation and deployment in the previous period, on August 12, 2017, the first fan of the Dashuikeng wind power project started to be hoisted.

Posted on 2017-08-12 03:31

The First Batch of Tower Pylons of Dashuikeng Wind Power Project Arrived at the Site as Planned

On July 10, 2017, the first V110-2MW wind turbine tower was delivered to the construction site of Dashuikeng Wind Power Project on time.

Posted on 2017-07-10 03:15

Keep Excelsior and Meticulous——The set-up work of the first wind turbine cage of Dashuikeng Wind Power Project successfully completed

V110-2MW wind turbine adopted by Dashuikeng wind power project is the first Vestas turbine that uses the anchor cage foundation in the China market.

Posted on 2017-05-30 01:38

Construction of Dashuikeng 110kV Booster Station Kicks off

After nearly a month of intense preparation and planning, the work of “three supplies and one leveling” for the Dashuikeng wind power project was successfully completed.

Posted on 2017-06-20 09:53

Planning and Development Department Actively Cooperate to Advance the Progress of the Project

On May 24, 2017, the 300,000kW wind power project of Hanas Group’s Yanchi Dashuikeng formally obtained the Opinion on Land Reclamation Review from Ningxia Autonomous Region’s Department of Land and Resources.

Posted on 2017-05-24 09:05

Planning and Development Department Actively Cooperate to Speed up the Dashuikeng 300,000 kilowatts Wind Power Project Construction Progress

Since 2017, the Planning and Development Department of Ningxia Hanas New Energy Group actively cooperated with the design of 300,000 kilowatts of Dashuikeng wind power project under construction in Ningxia Yanchi wind farm

Posted on 2017-07-22 03:23

Flexible Approaches Adopted to Address Sever Cold Weather to Guarantee Smooth Construction of Dashuikeng Wind Farm Project

From October 6 to 10, 2017, Ningxia’s Yanchi County was hit by an unexpected cold surge, followed by a heavy snowfall as the temperature plummeted to minus 10 degrees.

Posted on 2017-10-12 03:38

Dashuikeng 110kV Booster Station Starts Its Electrical Equipment Installation Phase

After nearly three months of intense construction, Dashuikeng 110kV booster station already has been prepared for its outdoor primary electrical equipment installation.

Posted on 2017-07-04 03:21

Hanas Chairman Ma Fuqiang and His Entourage Inspect Dashuikeng and Shijiawan Wind Power Projects

On June 18, 2017, Hanas Group Chairman Mr. Ma Fuqiang and his entourage inspected Dashuikeng and Shijiawan wind power projects.

Posted on 2017-06-18 02:39

Completion of the First Foundation Pit Excavation of Dashuikeng Wind Power Project

The first foundation pit excavation of turbine foundation of Dashuikeng wind power project was completed on April 27, 2017.

Posted on 2017-04-28 01:36

Quality First – the Bidding of Primary & Secondary Electrical Equipment of Dashuikeng 110kV Booster Station Successfully Concluded

February 2017, Ningxia Hanas New Energy Group organized the bidding of Dashuikeng 110kV booster station primary & secondary electrical equipment.

Posted on 2017-02-24 09:50

The Early Stage Work of Dashuikeng 300,000kW Wind Power Project Integration in an Orderly Manner

In order to make full preparations in the early stage of grid connection for Dashuikeng 300,000kW wind power project

Posted on 2017-08-01 06:51

Dashuikeng Wind Power Project Marks the Completion of Erecting All Angle Steel Towers Along 110kV Transmission Line

On September 8, 2017, 62 angle steel towers (572t in total) covered by the 110kV transmission line from 110kV booster station in Dashuikeng to 330kV substation in Songbao were all assembled and erected.

Posted on 2017-09-08 03:34

The First Five Sets of Wind Turbine Equipment of Dashuikeng Wind Power Project Arrive at the Site as Planned

On June 30, 2017, the first five sets of V110-2MW wind turbine equipment (engine room, hub, blades, etc.) were delivered to the construction site of Dashuikeng wind power project on time.

Posted on 2017-06-30 03:18

Safety is Our First Priority at All Times ——Construction Project Department Holds Fire Emergency Drills

As the Chinese saying goes that “Hidden danger is more perilous than the open flame, prevention is better than disaster relief, the responsibility is as extremely heavy as Mount Tai,”

Posted on 2017-06-15 01:41

Closed-Loop Management Enhances Execution Efficiency

Since the start of the construction of Dashuikeng wind power project, Hanas constructors were confronted with complicated external construction environment and urgent task objectives.

Posted on 2017-06-05 01:30

Turbine Model for Dashuikeng and Shijiawan Wind Farms Chosen

From October 2016 to January 2017, the management of Ningxia Hanas New Energy Group and technical staff of Hanas Engineering Construction and Management Company jointly conducted field research and visited domestic turbine manufacturers

Posted on 2017-01-23 09:26

Planning and Development Department Started the Second Phase of Initial Location Reconnaissance and Micro-Siting of Fengjigou 200MW Wind Power Project in Yanchi

On October 23, 2017, the Planning and Development Department started the preliminary stage of site reconnaissance and micro-siting of the 200MW wind power project in Yanchi, Wuzhong, Ningxia.

Posted on 2017-10-23 06:15

In order to conscientiously carry out the Group safety work requirements and implement the safety production and safety...